Monday, June 6, 2016

BHEL commissions 3 supercritical thermal units in Uttar Pradesh

BHEL BSE 0.25 % today announced the commissioning of all the 3 supercritical units of the 1980 MW coal-based Lalitpur Super Thermal Power Project in Uttar Pradesh within a span of just 85 days. Located in Lalitpur, Bundelkhand district, the 3x660 MW Lalitpur STPP has been developed by Lalitpur Power Generation Company Ltd , promoted by the Bajaj Hindusthan BSE -0.21 % group. "This has been achieved as a result of enhanced focus on project execution by way of innovative erection techniques and meticulous project management," the company said in statement. The main plant package contract of this 1980 MW power plant is being executed by BHEL. more at: http://economictimes.indiatimes.com/industry/energy/power/bhel-commissions-3-supercritical-thermal-units-in-uttar-pradesh/articleshow/52622232.cms