Tuesday, May 6, 2008

BHEL bags order from Chattisgarh

BHEL has secured orders from Chattisgarh State Electricity Board for supply and instalation of Rs 3.368 crore Main Plant Package at two power projects in Chhattisgarh, involving three coal-based units of 500 MW each.

The orders envisaged setting up of one unit of 500 MW at Korba West Thermal power project and two units of 500 MW each at the upcoming Marwa thermal power project, a BHEL press release said here.

Stated for synchronisation during the 11th Plan, these units will add 36 million units every day to the grid on commissioning.

BHEL's scope of work in the contract includeed design, engineering, manufacture, supply, erection and commissioning of Steam Turbines, Generators, Boilers (from Tiruchirappalli Unit), associated Auxiliaries, Piping and electricals besides state of the art Controls and Instrumentation which would be produced by BHEL Bangalore unit, it said.


Source:
http://www.hindu.com/thehindu/holnus/006200805070940.htm

No comments: