Bharat Heavy Electricals Ltd (BHEL) has set up a taskforce through which it is planning to seek Green Channel for speeding up transit of consignments bound for power projects, through inter-state borders.
The public sector company said that the task force will take up the idea to the Ministry of Surface Transport.
Addressing a Transporters' Meet & Awards function organised at BHEL Tiruchirappalli, A V Krishnan, executive director, BHEL – Tiruchirappalli said that this would be a significant benefit both for manufacturers and transporters of equipment for power projects across the country and would help to speed up project execution.
Unlike in the past when setting up the rail link used to be the first step in project execution enabling use of the railways, now there is not much time and roads are the only way, he added for transportation of project consignments, the speed at which the Indian power sector was growing meant that there was no longer time for setting up such infrastructure and construction had to start almost as soon as the land for the project was acquired.
more at:
http://sify.com/finance/bhel-may-seek-green-channel-news-news-kghbvAffjcg.html
Monday, June 7, 2010
BHEL commissions gas-based power projects in UAE, Oman
BHEL on Monday said it has commissioned two gas-based power projects in the United Arab Emirates (UAE) and Oman.
“BHEL commissioned the 2x42-MW gas turbine-based power project of Al Ghail Power Company in Ras Al Khaima, near Dubai, and a 26 MW gas turbine generator at Oman refinery and petrochemical plant in Muscat,” a company statement said.
BHEL’s scope of work under the 2x42-MW project included supply of gas turbine generating units with auxiliary equipment and supervision of erection and commissioning.
In the Middle East, BHEL has already set up 14 power projects, besides substations, and supplied a host of equipment for the power and oil and gas sectors.
BHEL currently manufactures equipment that can generate 15,000 MW of electricity.
ref:
http://beta.thehindu.com/business/companies/article448963.ece
“BHEL commissioned the 2x42-MW gas turbine-based power project of Al Ghail Power Company in Ras Al Khaima, near Dubai, and a 26 MW gas turbine generator at Oman refinery and petrochemical plant in Muscat,” a company statement said.
BHEL’s scope of work under the 2x42-MW project included supply of gas turbine generating units with auxiliary equipment and supervision of erection and commissioning.
In the Middle East, BHEL has already set up 14 power projects, besides substations, and supplied a host of equipment for the power and oil and gas sectors.
BHEL currently manufactures equipment that can generate 15,000 MW of electricity.
ref:
http://beta.thehindu.com/business/companies/article448963.ece
AC drilling rigs, a new drive for Bhel
Bharat Heavy Electricals Ltd (Bhel), Hyderabad, is poised to enhance its rig manufacturing capabilities in collaboration with National Oil Well Varco, US. The Hyderbad unit has signed an MoU with the US company late last month for manufacturing land drilling rigs that work on alternating current (AC) and support up to 2000 horse-power drilling lines. The MoU is for building 35 rigs in phases.
With this new technology, which is more efficient and environment-friendly, Bhel Hyderabad looks to double its annual turnover from oil rigs to Rs 400 crore from Rs 200 crore now, according to CSR Murthy, head of engineering & technology, oil rigs. The public sector company expects an order from ONGC for six of 2,000 HP AC deep drilling rigs, each rig costing about Rs 110 crore.
The AC drilling rig, introduced in 1994, is now a preferred technology in off-shore and onshore explorations for its high response.
Further, unlike DC rigs, which causes diesel emissions, AC rigs draw power mostly from utilities, and are, thus, more environment-friendly
ref:
http://www.financialexpress.com/news/AC-drilling-rigs--a-new-drive-for-Bhel/630184/
With this new technology, which is more efficient and environment-friendly, Bhel Hyderabad looks to double its annual turnover from oil rigs to Rs 400 crore from Rs 200 crore now, according to CSR Murthy, head of engineering & technology, oil rigs. The public sector company expects an order from ONGC for six of 2,000 HP AC deep drilling rigs, each rig costing about Rs 110 crore.
The AC drilling rig, introduced in 1994, is now a preferred technology in off-shore and onshore explorations for its high response.
Further, unlike DC rigs, which causes diesel emissions, AC rigs draw power mostly from utilities, and are, thus, more environment-friendly
ref:
http://www.financialexpress.com/news/AC-drilling-rigs--a-new-drive-for-Bhel/630184/
Friday, June 4, 2010
BHEL's industry segment registers 40-per cent growth news
Bharat Heavy Electricals Limited (BHEL) today said that its industry sector business segment recorded an all-time high growth of 40 per cent over the previous year.
Out of the total order booking of Rs59,031 crore by BHEL in 2009-10, industry business segment contributed Rs.14,366 crore, it said.
BHEL said that during fiscal 2009-10, major successes included the highest value captive power plant order of Rs3,348 crore for oi8l marketing gioant, Indian oil Corporation's cogeneration power plant at Orissa, major repeat orders from Hindalco for 6x150 MW BTG package for its Orissa project and Chennai Petroleum Corporation Limited (CPCL) for a 20 MW cogeneration plant at its Chennai Refinery.
BHEL's transportation segment is executing its single largest order of Rs990 crore for 150 5000 HP 25 kV AC mainline electric locomotives (type WAG -7) from Indian Railways.
ref:
http://www.domain-b.com/companies/companies_b/Bharat_Heavy_Electricals/20100604_industry_segment.html
Out of the total order booking of Rs59,031 crore by BHEL in 2009-10, industry business segment contributed Rs.14,366 crore, it said.
BHEL said that during fiscal 2009-10, major successes included the highest value captive power plant order of Rs3,348 crore for oi8l marketing gioant, Indian oil Corporation's cogeneration power plant at Orissa, major repeat orders from Hindalco for 6x150 MW BTG package for its Orissa project and Chennai Petroleum Corporation Limited (CPCL) for a 20 MW cogeneration plant at its Chennai Refinery.
BHEL's transportation segment is executing its single largest order of Rs990 crore for 150 5000 HP 25 kV AC mainline electric locomotives (type WAG -7) from Indian Railways.
ref:
http://www.domain-b.com/companies/companies_b/Bharat_Heavy_Electricals/20100604_industry_segment.html
Wednesday, June 2, 2010
BHEL sets up new unit at Jhansi facility
BHEL on Wednesday said it has increased its transformer building capacity to 15,000 megavolt ampere (MVA) per annum by setting up a new unit at its facility at Jhansi in Uttar Pradesh.
BHEL has set up a new Core and Tank Shop at its transformer manufacturing facility at Jhansi, thereby enhancing the manufacturing capacity from 8,500 MVA to 15,000 MVA per annum, a company statement said.
“These steps would enable BHEL to cater to the requirements of power stations with advanced technology that are expected to come up,” Vilasrao Deshmukh, the Minister for Heavy Industries & Public Enterprises, said after dedicating the unit to the nation on Wednesday.
more at:
http://beta.thehindu.com/business/companies/article444659.ece
BHEL has set up a new Core and Tank Shop at its transformer manufacturing facility at Jhansi, thereby enhancing the manufacturing capacity from 8,500 MVA to 15,000 MVA per annum, a company statement said.
“These steps would enable BHEL to cater to the requirements of power stations with advanced technology that are expected to come up,” Vilasrao Deshmukh, the Minister for Heavy Industries & Public Enterprises, said after dedicating the unit to the nation on Wednesday.
more at:
http://beta.thehindu.com/business/companies/article444659.ece
BHEL Augments Transformer Manufacturing Capacity
As part of its holistic manufacturing capacity expansion and modernization programme, Bharat Heavy Electricals Ltd., or BHEL, has set up a new core and tank shop at its transformer manufacturing Facility at Jhansi in Uttar Pradesh.
With this new shop, the manufacturing capacity for transformers at its Jhansi unit is enhanced to 15,000 MVA per annum from 8,500 MVA per annum and is progressing well to further augment it to 20,000 MW by 2012 to meet the power demand of the nation.
The unit was dedicated to the nation on Wednesday by Vilasrao Deshmukh, Union Minister for Heavy Industries and Public Enterprises in the presence of Arun Yadav, Union Minister of State for Heavy Industries and Public Enterprises and Pradeep Jain Aditya, Union Minister of State for Rural Development. B.S. Meena, Secretary, Department of Heavy Industry and B.P. Rao, CMD, BHEL, were also present on the occasion, in addition to the Board of Directors and other senior officials of BHEL.
Earlier, in his welcome address, Rao said that the India's target of adding 78,700-MW of generation capacity in the 11th Plan and around 1,00,000-MW in the 12th Plan calls for large scale evacuation of power and efficient transmission over long distances. This new facility has been established with the objective of meeting the emerging business opportunities in transmission and distribution. This will not only increase BHEL's manufacturing capacity but also give an opportunity to position itself as the leading player in the segment, he added.
Copyright(c) 2010 RTTNews.com, Inc. All Rights Reserved For comments and feedback: contact editorial@rttnews.com
ref:
http://www.stockmarketsreview.com/news/11085/
With this new shop, the manufacturing capacity for transformers at its Jhansi unit is enhanced to 15,000 MVA per annum from 8,500 MVA per annum and is progressing well to further augment it to 20,000 MW by 2012 to meet the power demand of the nation.
The unit was dedicated to the nation on Wednesday by Vilasrao Deshmukh, Union Minister for Heavy Industries and Public Enterprises in the presence of Arun Yadav, Union Minister of State for Heavy Industries and Public Enterprises and Pradeep Jain Aditya, Union Minister of State for Rural Development. B.S. Meena, Secretary, Department of Heavy Industry and B.P. Rao, CMD, BHEL, were also present on the occasion, in addition to the Board of Directors and other senior officials of BHEL.
Earlier, in his welcome address, Rao said that the India's target of adding 78,700-MW of generation capacity in the 11th Plan and around 1,00,000-MW in the 12th Plan calls for large scale evacuation of power and efficient transmission over long distances. This new facility has been established with the objective of meeting the emerging business opportunities in transmission and distribution. This will not only increase BHEL's manufacturing capacity but also give an opportunity to position itself as the leading player in the segment, he added.
Copyright(c) 2010 RTTNews.com, Inc. All Rights Reserved For comments and feedback: contact editorial@rttnews.com
ref:
http://www.stockmarketsreview.com/news/11085/
Tuesday, June 1, 2010
Singareni to buy power equipment from BHEL
State-owned mining company Singareni Collieries Company Limited (SCCL), which is setting up a 600 Mw in Jaipur mandal of Adilabad district, would place orders for the power plant equipment from BHEL in July. The company would call for bids for the balance of plant in October.
Speaking to Business Standard, SCCL chairman and managing director S Narsing Rao said it would take 36 to 40 months for the project to complete once the zero date starts in October.
SCCL preferred to place the order with BHEL on a nomination basis. The power plant equipment would cost about Rs 1,300 crore while the balance of the plant about Rs 1,150 crore. The total cost of the project is pegged at Rs 2,700 crore in a 70-30 debt equity ratio.
more at :
http://www.business-standard.com/india/news/singareni-to-buy-power-equipmentbhel/396700/
Speaking to Business Standard, SCCL chairman and managing director S Narsing Rao said it would take 36 to 40 months for the project to complete once the zero date starts in October.
SCCL preferred to place the order with BHEL on a nomination basis. The power plant equipment would cost about Rs 1,300 crore while the balance of the plant about Rs 1,150 crore. The total cost of the project is pegged at Rs 2,700 crore in a 70-30 debt equity ratio.
more at :
http://www.business-standard.com/india/news/singareni-to-buy-power-equipmentbhel/396700/
Subscribe to: